ADO Local Pre-release

Manual

Boards and planning

How a Team plans and runs its work in ADO Local: the Team Backlog and its Kanban Board, an Iteration's Backlog, Taskboard and Capacity, the stand-up and the end of a sprint, Delivery Plans across Teams, retrospectives, and the Areas and Iterations they all depend on.

Teams

Planning in Azure DevOps belongs to a Team, and so it does here. The sidebar shows one Team at a time, the active Team: its name, then its Backlog, its Iterations (the current one marked Current, with the one before it and the next two) and its Retrospectives.

Switch Team

  1. Click the Team's name in the sidebar to open the Team menu.
  2. Choose another Team. Your own Teams are listed first.

The command palette has Switch Team: … for each Team too. Opening a link to another Team's Iteration or backlog makes that Team the active one. All Iterations…, under the Team's Iterations in the sidebar, lists every Iteration the Team has, beyond the few shown there.

The Team menu also has the Team's Work Item templates, Import from CSV… and Team settings… (see Team settings).

The Team Backlog

Backlog in the sidebar opens the Team's backlog: one backlog level at a time, across every Iteration, in Backlog Order. Choose the level along the top (Epics, Features, Stories or Backlog items, as the Process names them). Beside the levels, the backlog has five views: Backlog, Board, Analytics, Dependencies and, under the hourglass, Needs attention. The one you used last opens next time.

The Team Backlog at the Stories level, with an Epic and a Feature shown as parents above their stories, each row's State, Iteration and Story Points, and the Planning panel listing Iteration 42 and Iteration 43
The Stories level with Parents on: the Epic and Feature above each story, and the Planning panel on the right.

What the toolbar does

When the window is narrow, the toggles move into View options and the levels become a menu, so nothing is cut off.

Order the backlog

Drag a row up or down to change its Backlog Order. From the keyboard, select a row with J and K, then press ⌥↑ or ⌥↓ to move it. The new order is saved to Azure DevOps, so the website shows it too.

Plan a Work Item into an Iteration

  1. Drag a row onto an Iteration in the Planning panel, or onto an Iteration in the sidebar.
  2. Let go. The Work Item moves to that Iteration, and its unfinished child tasks go with it; a message says so.

The same works from other lists: drag a Work Item from Search or a Query onto an Iteration in the sidebar. A Work Item's open panel follows the move. Offline, the move waits to be sent.

Tasks on the backlog

At the backlog items' level, → shows a selected row's tasks under it and ← hides them again. The buttons in the toolbar's header show or hide every backlog item's tasks at once. A task's Remaining Work shows beside it.

The Team Backlog at the Features level, listing the Features with their States and Iterations
Another level of the same backlog: the Features.

Forecast and Rollup

Forecast

Forecast draws a line across the backlog where each coming Iteration would end, from a velocity you set: how much effort the Team gets done in an Iteration. It starts at Analytics' average over the last six Iterations; type another number in the box beside Forecast to see what a faster or slower Team would reach. Each line is labelled with the Iterations it divides.

Rollup

Rollup adds columns worked out from each Work Item's descendants: progress by count of Work Items or by effort (as a bar and a percentage), the total effort, and the total Remaining Work. It's most useful on the Features and Epics levels, to see how far along each one is. Tree Queries offer the same rollup columns.

The Team Backlog with Forecast on at a velocity of 6, a line marking where Iteration 42 ends and Iteration 43 begins, and Rollup's progress bars on the parents
Forecast at a velocity of 6 marks the line between Iteration 42 and Iteration 43; Rollup shows each parent's progress.

Filtering backlogs and boards

The Team Backlog's list and its Kanban Board, and an Iteration's Backlog and its Taskboard, can be filtered by words. Press F or click the filter button, and type.

The Team Backlog filtered by a word, showing only the matching rows under their parents, with a count of how many were found
A filter on the Team Backlog keeps the parents of what it finds, so you can see where each one sits.

On the boards:

While a filter is on:

Tip

What you type goes with you from the Team Backlog to its Kanban Board, and from an Iteration's Backlog to its Taskboard. It's cleared when you open another Team's backlog or another Iteration. Nothing is saved.

The Kanban Board

Board shows the backlog level as the Team's Kanban Board: its columns, with WIP limits and Doing and Done splits, its Swimlanes, and a card for each Work Item showing the Fields the Team chose. Cards are coloured by the board's Styles and tags by its tag colours, as on the website.

The Stories Kanban Board with New, Active (split into Doing and Done), Resolved and Closed columns, WIP limits of 3 and 5, a Default lane and an Expedite lane, and cards coloured by Style with coloured tags
The column heads show WIP limits (3 / 3 here is full); Active is split into Doing and Done; the Expedite Swimlane sits under the default one.

Move cards

Offline, moves show straight away and wait to be sent.

Card age

Each card says how long it has been in its State, after the State: "Active · 5d", in weeks from a fortnight on. It counts from the date the State last changed, so where each column has a State of its own it's the card's time in that column; a split column's Doing and Done share one count, because Azure DevOps keeps no date for a column. A fortnight or more in a column where work is under way is drawn in amber. The last column's cards don't show an age.

Kanban cards each showing their State and how long they've been in it, such as New · 5d and New · 129w
Each card's age beside its State.

Board settings

The gear on a Kanban Board opens its settings, for the Team. Changes save for everyone in the Team and show on the website too, so the dialog says so at its top. Save for the Team saves them; Cancel leaves everything as it was.

Stories board settings on the Columns tab: each column with its name, WIP limit and Split box, one opened to show each Work Item type's State and its Definition of done
Columns: a name, WIP limit and Split for each, and opened out, each type's State and the Definition of done.

Columns

Swimlanes and cards

Styles

Styles are rules that colour cards. Each has a name, can be turned on or off, and sets a card colour, the title's colour, and bold, italic or underline. Its criteria are a Field, an operator and a value, joined by And, and can use @Me, @Today and @CurrentIteration. Rules are tried in order: a card takes the first Style it meets, so drag the most important to the top.

Board settings on the Styles tab: a list of rules, one opened to show its card colour, title colour and text style, and its criteria
Styles: each rule's colours and criteria, tried from the top.

Tag colours

Tag colours gives a tag a colour, and a colour for its text. The board draws both in light and dark, keeping the text readable on any colour.

Board settings on the Tag colours tab: tags each with a background and text colour
Tag colours: a background and a text colour for each tag.
Permissions

Team administrators and Project administrators can change board settings. For anyone else they show greyed out, with the reason. They need a connection. The Taskboard's own styles can't be read from Azure DevOps, so they stay on the website.

Needs attention

Needs attention, the hourglass beside Dependencies, lists the Team's Work Items at the backlog level that want looking at:

At the backlog items' level, their tasks are among them. Each row says its State and how long it has been in it, who has it, and how long it has been unchanged or which Iteration it was left in. One with both reasons is listed under both. Click a row to open the Work Item. Choose 7, 14 or 30 days at the top; the choice is remembered.

Needs attention: Work Items unchanged for days and Work Items left in Iterations that are over, each with its State, person and how long
What's gone quiet, and what was left in an Iteration that's over.

An Iteration is over once its last day has passed; one that runs alongside the current one, such as a release's, isn't. Needs attention reads this computer's copy, so it works offline and changes as Work Items do. It only looks through what the Sync Scope keeps: by default, Work Items changed in the last year and yours.

Team analytics

Analytics charts the backlog level from Azure DevOps Analytics:

Team analytics for Stories: a velocity chart of the last 6 Iterations, a cumulative flow chart of the last 30 days by State, and a cycle time chart of the last 90 days
Velocity, cumulative flow and cycle time, each with its own period and a refresh button.
Personal Access Token

Team analytics comes from Analytics, so a Personal Access Token needs Analytics: Read. Where Analytics is turned off for the Project, the tab says so.

Dependencies

Dependencies shows the Team's Work Items that have Predecessor or Successor links, in a column for each Iteration, with a line from each predecessor to the Work Item waiting on it. Ours shows the dependencies between the Team's own Work Items; Others adds those with other Teams.

The Dependencies tab: Iteration 41, 42 and 43 as columns, cards joined by lines, one line red because its successor is planned first, and a Work Item's Links listing its Predecessor and Successor in the panel beside it
A red line: #4377 in Iteration 41 waits on #4551 in Iteration 42. The Work Item's Links warn about it too.

Add, reverse or remove a dependency

A toggle in the toolbar also shows the Work Items in the current and future Iterations that have no dependencies yet, to drag from or onto.

Iterations

Click an Iteration in the sidebar to open it. Its header shows its dates, how many days are left, a small burndown with how much is done and how much was added since it started, and the Remaining Work left. Below the header, if the organization has the Sprint Goal extension, is the Team's goal for the Iteration. The Iteration has four tabs: Backlog, Taskboard, Capacity and Stand-up. It opens on the one you used last.

Iterations are read from this computer's copy, then checked with Azure DevOps, so Work Items outside the Sync Scope that belong to the Iteration still appear. A Work Item made from an Iteration goes into that Iteration and the Team's Area.

The Iteration Backlog

The Iteration's backlog items in Backlog Order, each with its tasks underneath. Above the list, Work details shows the Team's and each person's Remaining Work against the Capacity they have left; red means more work than time.

Iteration 42's Backlog: its backlog items with their tasks underneath, Work details above showing each person's Remaining Work against Capacity
An Iteration's Backlog, with Work details along the top.

The Taskboard

A Swimlane for each backlog item, with its tasks as cards in the Team's Taskboard columns (or the task types' States). Drag a card to another column to change its State; only moves the Process allows are accepted. From the keyboard, ⌥← and ⌥→ move a focused card a column.

Iteration 42's Taskboard: backlog items down the left, their tasks as cards in New, Active and Closed, Remaining Work totals at the top of each column, and person chips with each person's work against Capacity
The person chips at the top filter the board to one person's tasks; each column's head totals its Remaining Work.

Swimlanes by person

Columns on the Taskboard groups Swimlanes by backlog item or by person. By person, everyone with tasks in the Iteration gets a Swimlane, and each shows the hours they've completed beside their Remaining Work; the header does the same for the whole Team. Drag a card into another person's Swimlane to reassign it.

The Taskboard grouped by person: a Swimlane for each person with their Remaining Work and hours completed, and tasks in New, Active and Closed
Swimlanes by person, each with the work left and the hours completed.

Hours completed are a number Field added up over each person's done tasks: Completed Work where the Process's tasks have it (Agile, CMMI), otherwise a Field named for work complete. Columns › Hours completed picks another Field, or counts done tasks instead.

What cards show

The Taskboard's Columns menu: group Swimlanes by backlog item or person, Hours completed, Show tags on cards, Card Fields and Hide people with no work left
The Taskboard's Columns menu.

These choices are kept for each Team on this computer.

Capacity

Capacity is how many hours each Team member can give the Iteration. It's saved to Azure DevOps, as the website's Capacity tab is.

Iteration 42's Capacity: the Team's days off, and for each member their Activities with hours a day, their days off, and their work against Capacity left as a bar
Each member's Activities and hours a day, days off, and work against Capacity left.

The line at the top adds it up: working days left, the Team's Capacity and its Remaining Work. Offline, Capacity changes wait to be sent; when they go, the last change wins for each person, as on the website.

The burndown

Click the small burndown in an Iteration's header to open the full chart beside the Iteration. It shows Remaining Work each day against the ideal trend and the Team's Capacity left; Backlog items switches it to count backlog items instead of hours. Figures across the top give the Remaining Work, the share done and the change of scope since the Iteration started. Rest the pointer on a day to see its numbers.

The burndown beside Iteration 42: Remaining Work 9h, Done 61%, Scope change +1, and a chart of Remaining Work, the ideal trend and Capacity left by day
The burndown: Remaining Work, the ideal trend and Capacity left, day by day.

The burndown comes from Analytics. Without Analytics: Read, it's worked out from each Work Item's history instead, which is slower.

Stand-up

Stand-up, beside an Iteration's Backlog, Taskboard and Capacity, is for the daily stand-up: the Iteration's Work Items, backlog items and tasks alike, by whose they are, in the order of their names, then the ones nobody has. Open it from the Iteration, or with Current Stand-up in the command palette.

The Stand-up for Iteration 42: a sentence summing up since yesterday, then each person with their Work Items grouped as changed State since yesterday, under way and not started, each with its State and how long
Each person's work, grouped by what's happened since the last working day.

A sentence heads it, such as "Since yesterday: 1 changed State. 5 others under way." Then each person's Work Items are in four groups:

A Work Item is under whoever has it now; a closed one is under whoever closed it, then says who has it now. What's under way with no change at all for a week says so in amber. A task says which backlog item it's under. Click a row to open the Work Item.

"Since" means since the Team's last working day, so on a Monday the weekend counts with Friday. The working days, days off and members come from the Iteration's Capacity. Stand-up reads this computer's copy, so it works offline. It goes by States: a reassignment, a Comment or a Work Item added to the Iteration isn't a change it lists. An Iteration that's over, or hasn't started, says so.

Sprint Goal

Where the organization has the Sprint Goal extension, each Iteration's Backlog, Taskboard, Capacity and Stand-up start with the Team's goal for it. The Home sprint tile shows it too.

The Sprint Goal line at the top of Iteration 42's Backlog, with Details and Achieved beside it
The goal at the top of the Iteration, with Details and Achieved.
The Sprint Goal's Details opened under the goal, with formatted text
The goal's Details, opened in place.

It's the same goal the website's Goal tab and widget show, saved the way the extension saves it. If someone else saved the goal since you opened it, you're asked which to keep. Goals show offline as last read, and change only with a connection. Without the extension, there's no goal line.

Personal Access Token

A Personal Access Token needs Extension Data: Read & write, and Extensions: Read to check the extension is installed.

Sprint report

Once an Iteration has started, the Sprint report button in its header (the clipboard) opens a report of what was planned against what was done. It compares the Iteration's backlog items as they were at the end of its first day, once planning was done, with how they stood at the end of its last day, or stand now while it's still going.

The Sprint report for Iteration 42: a sentence on how the plan went, figures for Planned, Completed, Added after the start, Still open, Moved out and Removed, and the backlog items listed by what became of them
How the plan went, in a sentence, six figures and a list.

Copy as Markdown puts the whole report on the clipboard, to paste into notes, a Wiki page or a chat.

Moved out means no longer among the Team's backlog items in the Iteration: in another Iteration, another Team's Area, or changed to a type that isn't a backlog item. The effort planned is the estimate at the start; the rest is the estimate at the end. A day ends at this computer's midnight. The report covers the Team's backlog items, not their tasks; it needs a connection but not Analytics, and nothing is kept.

Roll over

At the end of a sprint, Roll over (the button beside Sprint report in an Iteration's header) moves what's unfinished to a later Iteration in one go.

  1. Click Roll over. The dialog lists the Iteration's unfinished backlog items in Backlog Order, all ticked, then any unfinished tasks on their own (whose backlog item is closed or in another Iteration).
  2. Choose where they go in Move to: the Team's Iterations that aren't over, the next one first, each with its dates; or the Team's backlog, which takes them out of every Iteration.
  3. Untick anything that should stay. The line under the list says how many will move and how many stay.
  4. Click the button that says how many will move, such as Move 10 Work Items. Each backlog item takes its unfinished tasks in the Iteration with it.
The Roll over Iteration 42 dialog: Move to Iteration 43, seven unfinished backlog items ticked, and a note that 7 backlog items and 3 tasks will move and 2 closed tasks stay
Roll over: what will move, and what stays as what the Iteration did.

Only what's listed moves: a task of a listed backlog item that's in another Iteration stays there. What's closed stays where it is, as what the Iteration did. Undo, on the message that says they've moved, puts them all back. Offline, the moves wait to be sent. A Work Item that turns up while the dialog is open is listed unticked. Roll over is there for the current Iteration too, for a Team that moves things on before its last day.

Delivery Plans

Plans in the sidebar (and the command palette) lists the active Team's Project's Delivery Plans. A plan shows a row for each Team and backlog level, the Teams' Iterations along the dates, their Work Items as cards, the plan's markers, and today.

A Delivery Plan with rows for two Teams, their Iterations from 15 September to 24 November, a Feature card in Iteration 42, a red line for today and a green Passkeys GA marker
A plan: a row per Team, a card per Work Item, today in red and a marker in green.

Make or change a plan

+ beside Plans makes a new plan with its first Teams and backlog levels. Plan settings on a plan changes it:

Plan settings on the Teams tab: the plan's Teams, each with a backlog level, to add, remove and reorder
Plan settings: the Teams tab.

Plan settings also deletes the plan, after asking.

Needs a connection

Plan settings save straight to Azure DevOps, for everyone. If someone else saved the plan first, the settings reload as they are now.

Retrospectives

Where the organization has the Retrospectives extension, Retrospectives under the active Team in the sidebar lists the Team's retrospective boards, newest first, with the phase each is in. The newest board is listed under it in the sidebar too. You take part alongside people on the website: the board is read again every 10 seconds while it's on screen, so others' cards and votes appear on their own.

Start a board

  1. Open Retrospectives and click New board.
  2. Give it a name, and choose a template: Start, Stop, Continue; Good, Improve, Ideas, Thanks; Mad, Sad, Glad; 4Ls; DAKI; KALM; Went Well, Learned, Accelerators, Impediments; or Speedboat.
  3. Set Votes each person has (1 to 12), and tick Anonymous to leave authors off the cards. That can't be changed once the board is made.
  4. Click Make board. It starts collecting cards. Making a board needs a connection.

The four phases

A board goes through Collect, Group, Vote and Act, shown as steps in its header. Clicking a step only looks at the board that way here. Whoever made the board moves it on for everyone with Move everyone to …, and the website follows.

Collect

Everyone writes cards. Type in Add a card… at the top of a column and press Enter. You can edit your own cards, and delete them while they have no votes. If someone else edited the same card meanwhile, you're asked which words to keep.

A retrospective board in Collect: Good, Improve, Ideas and Thanks columns, each with Add a card at the top and cards with their authors
Collect: a card box at the top of each column.

Group

Drag a card onto another to group them; the group shows how many cards it has. From the keyboard, a card's Group with… does the same. Drag a card onto a column's space to take it out of its group.

A retrospective board in Group: cards with Group with buttons, and a group of two cards opened under one
Group: drag a card onto another, or use Group with….

Vote

Each person spends the board's votes on the cards that matter most. The header says how many you have left; take a vote back with −. On an anonymous board, cards show no authors.

Act

Cards are listed with the most votes first. Make a Work Item from a card with Create Work Item, or link one that exists with Link…; it opens in a panel, and the card shows it with its State.

A retrospective board in Act: Start, Stop and Continue columns with cards ordered by votes, a linked Work Item on one, and Create Work Item and Link buttons
Act: the most-voted cards first, each ready to become a Work Item.

Offline, a board shows as it was, marked as out of date, and nothing can be changed. Archived boards stay on the website.

Project settings: Areas and Iterations

A Project's … menu in the sidebar (or Areas and Iterations in the command palette) opens its Project settings: the Areas and the Iterations as two trees, with each Iteration's dates and how many Work Items this computer has at each node. Type in the filter to find one.

Project settings for Contoso Web on the Iterations tab: a tree of Iterations with their dates, lengths and Work Item counts, and the keys to change them along the bottom
The Iterations tree. The keys that change it are along the bottom.

Select a node, then:

KeyDoes
EnterRename it in place
NAdd a child under it
⇧NAdd one beside it
DSet an Iteration's dates
MMove it (or drag it onto another node)
+Add the next Iteration after a dated one
⌫Delete it, choosing where its Work Items go

Add the next Iteration

+ on a dated Iteration offers the next one: starting the next working day, as long as the one before, its number one higher. Change anything before adding it. Leave Add it to the Team's Iterations ticked and it shows in the sidebar and the Team's backlog straight away.

The Add next Iteration dialog: Iteration 44, starting 9 November and finishing 20 November, 12 days, with Add it to Phoenix's Iterations ticked
The next sprint, worked out from the last one.

Renaming and moving keep every Work Item: Azure DevOps moves their paths, and the pickers, the sidebar and the local copy follow at once. Deleting a node asks where its Work Items go: its parent, unless you pick another.

Permissions

Azure DevOps is asked first what you may change. Without permission, or offline (where the trees show as last read), everything is read only and says why. A Personal Access Token needs Work Items: Read & write to make changes.

Team settings

Team settings… in the Team menu sets which Areas and Iterations a Team uses. Changes are saved for the whole Team, and its backlog, boards and Iterations follow them, here and on the website.

Phoenix settings on the Iterations tab: the Backlog Iteration, the Default Iteration set to the current Iteration, and the Team's Iterations ticked, with Save for Phoenix
Team settings: the Backlog Iteration, the Default Iteration and the Team's Iterations.

As with Project settings, Azure DevOps is asked first what you may change; without permission the settings are read only, with the reason.